Laserfiche WebLink
Time Line For the completion of the new rink in the Barn <br /> <br />May 3rd - Removal of the existing boards <br /> <br />May 10th -- Demo of the concrete <br /> <br />May 24th - Install curb to outer slab <br /> <br />May 31 st_ Sub Grade prep A. Insulation <br /> B. Vapor Barrier <br /> C. Refrigeration pipes <br /> D. Headers <br /> <br />July 12th - Concrete: <br /> <br />A. Rebar <br />B. Wire mesh <br />C. Expansion joint <br />D. Pour concrete <br />E. Completion of expansion joints <br /> <br />August 23rd - Completion of Floor <br /> <br />August 23ra - Insulation of boards <br /> <br />September gth _ Substantial Completion of project, punch items may remain <br /> <br />september 15th- Final Completion of Project <br /> <br />September 19th - start up of Compressors, ice by September 24th. <br /> <br /> <br />