Proposed Improvement Schedule <br />ItemCompletion Date <br />Submit Facility Plan to MPCA for review and approvalMarch 2013 <br />City requests placement on MPCA Project Priority ListMarch 2013 <br />MPCA reviews and approves Facility Plan.April –July 2013 <br />City requests placement on the MPCA 2013 Intended Use PlanMay 2013 <br />Prepare plans and specifications for the wastewater treatment facility August –November 2013 <br />improvements <br />2013 Intended Use Plan is approved by MPCA.September 2013 <br />Submit plans and specifications to MPCA for review and approval.December 2013 –February 2014 <br />City advertises, open bids, and accepts construction bids for facility March –April 2014 <br />improvements. <br />Initiate construction of wastewater treatment facility improvements.May 2014 <br />Complete construction of wastewater treatment facility improvements May 2016 <br />and meet discharge standards. <br />25 <br />