LAKE ORONO IMPROVEMENT PROJECT TIME LINE <br /> <br />January 1998 <br /> <br />· Determination of wetlands on disposal sites, with property owner's <br /> permission, by Natural Resources Conservation Service (NRCS). <br />· January 7 meeting with permitting governmental agencies. <br />· Preliminary assessment role (equivalency units) by January 15 meeting. <br />· State Disposal Systems permit (SDS) submitted to the Minnesota <br /> Pollution Control Agency (MPCA) - (180 days). <br />· Funding from Sherburne County sought. <br /> <br />February <br /> <br />· Protected Waters permit submitted to the Minnesota Department of <br /> Natural Resources (DNR) - (45 days). <br />· U.S. Army Corps of Engineer (USACE) permit submitted - (60 to 120 <br /> days). <br />· "401 Water Quahty Certification submitted to MPCA - (60-120 days). <br />· Environmental Assessment Worksheet (EAW) submitted to appropriate <br /> agencies - (approximately 60 days). <br />· None Point Discharge permit (NPDES) submitted to MPCA- (permit <br /> immediate after submittal). <br />· Feasibihty Study ordered by the City Council on 2/16/98. <br /> <br />March <br /> <br />· Feasibility received by City Council and Public Hearing ordered on 3/2/98. <br /> <br />April <br /> <br />· Public Hearing held and plans and specifications ordered by City Council <br /> on 4/13/98. <br />· Special Projects and Challenge Grant applications to repair erosion at <br /> Orono Cemetery submitted. <br />· DNR Protected Waters permit issued. <br /> <br />May <br /> <br />· Plans and Specifications approved and bids authorized by the City <br /> Council on 5/4/98. <br />· Bids advertised for 21 days. <br />· EAW process is completed. <br /> <br />s:Xb&z\steverXlakoagda.doc <br /> <br /> <br />