Laserfiche WebLink
Time Line For the completion of the new rink in the Barn <br />May 3'ti -Removal of the existing boards <br />May 10`n -Demo of the concrete <br />May 24tH -Install curb to outer slab <br />May 3151- Sub Grade prep <br />A. Insulation <br />B. Vapor Ban-ier <br />C. Refrigeration pipes <br />D. Headers <br />July 12tH -Concrete: <br />A. Rebar <br />B. Wire mesh <br />C. Expansion joint <br />D. Pour concrete <br />E. Completion of expansion joints <br />August 23rd - Comp]etion of Floor <br />August 23rtl -Insulation of boards <br />September 8`n -Substantial Completion of project, punch items may remain <br />September I S`n -Final Completion of Project <br />September 19tH -start up of Compressors, ice by September 24tH <br />