Bore Rig Work Order Data for last 3 years
<br />2010 Work Orders w/Bore Services Total Comment Likely In-House Likely Out-sourced
<br />10-03 $519.75 Midwest $519.75
<br />10-12 Engers Addn Rebuild $4,500.00 estimated $4,500.00
<br />10-14 Watson Rebuild $4,515.75 MP $4,515.75
<br />10-19 30tt J-box Changeout $4,320.00 MP $4,320.00
<br />10-20 1sU2nd Street Rebuild $46,751.75 Midwest $46,751.75
<br />10-22 Area 22 Rebuild $4,500.00 estimated $4,500.00
<br />10-29 5th Street Rebuild $49,969.50 estimated $49,969.50
<br />10-30 UHG Temp - 14100 Bus Center Dr. $4,500.00 estimated $4,500.00
<br /> $119,576.75 $119,576.75 $0.00
<br />2009 Wor k Orders w/Bore Services Total Comment Likely In-House Likely Out-sourced
<br />09-08-38 CTY 1 Rebuild $50,558.00 Underground Piercing $50,558.00
<br />09-14 $6,962.80 Midwest $6,962.80
<br />09-13 $788.50 Midwest $788.50
<br />09-16 $975.00 Midwest $975.00
<br />exp $5,059.60 Midwest $5,059.60
<br />09-10 CR 77 $399.75 Midwest $399.75
<br />09-18 191 1/2 Rebuild $16,838.45 Midwest $16,838.45
<br />09-20 Simonet Rebuild $13,987.10 Michels $13,987.10
<br />09-21 Xenia/Tipton Rebuild $11,950.00 Michels $11,950.00
<br />09-22 New GW Store $1,200.00 Midwest $1,200.00
<br />09-24 Area 23 Taps $3,697.00 Midwest $3,697.00
<br />09-26 HWY 101 crossing $13,004.50 Midwest $13,004.50
<br /> $125,420.70 $61,858.20 $63,562.50
<br />2008 Wor k Orders w/Bore Services Total Comment Likely In-House Likely Out-sourced
<br />08-26 $2,717.00 MP $2,717.00
<br />08-40 $540.00 MP $540.00
<br />exp Place Service $395.00 MP $395.00
<br />07-03 Misc Frost Trenching $1,683.75 Michels $1,683.75
<br />07-40 URD Trench Super Target $3,455.93 Michels $3,455.93
<br />08-03 Seviceinstall/frosttrench $1,628.75 $1,628.75
<br />OS-03 Sevice install/frost trench $1,465.30 Michels $1,465.30
<br />08-35 Elk Lake Rd $1,318.00 Michels $1,318.00
<br />08-18 Brentwood $108,375.00 Michels $108,375.00
<br />08-46 169 crossing $15,425.00 Michels $15,425.00
<br />08-44 Feeder 52 $6,000.00 Michels $6,000.00
<br />08-49 CR 39 - 3 Phase $9,000.00 Michels $9,000.00
<br />OB-20 $195.00 Midwest $195.00
<br />08-08 $844.00 Midwest $844.00
<br />exp $325.00 Midwest $325.00
<br />exp $201.25 Midwest $201.25
<br />08-11 Deerfield 86855.13 Midwest $86,855.13
<br />08-18 Brentwcod $931.25 Midwest $931.25
<br />08-40 Hwy 101 $325.00 Midwest $325.00
<br />08-51 MN School of Bus $7,973.50 Midwest $7,973.50
<br /> $249,653.86 $116,541.36 $133,112.50